Alinta Cooling Tower

Date

2011, 2012, 2013

Type

 Industrial

Client

Alinta Energy

Complete replacement of all the internal timber framing members. This project took place over three years during 4 week shut periods. The cooling tower is separated into three sections allowing two sections to continue running while work takes place on the other.

 

Work consisted of:

  • Full height scaffolding for the section of work to be completed on
  • Removal of exterior fiberglass cladding and internal baffles
  • Lay temporary platforms for access
  • Remove internal rotten timber, prop structure and replace with new pre-cut timber lengths
  • Replace internal baffles
  • Install new fiberglass cladding 

Related Projects