Alinta Cooling Tower
Date
2011, 2012, 2013
Type
Industrial
Client
Alinta Energy
Complete replacement of all the internal timber framing members. This project took place over three years during 4 week shut periods. The cooling tower is separated into three sections allowing two sections to continue running while work takes place on the other.
Work consisted of:
- Full height scaffolding for the section of work to be completed on
- Removal of exterior fiberglass cladding and internal baffles
- Lay temporary platforms for access
- Remove internal rotten timber, prop structure and replace with new pre-cut timber lengths
- Replace internal baffles
- Install new fiberglass cladding